How to track project costs and know whether a job made money
Many jobs look profitable on the quotation and lose money on site. Here is a simple job costing method for a Malaysian SME, from budget to final profit, with a worked RM example.

To track project costs, give each job a code, set a budget for each cost type before work starts, and record every supplier bill, purchase, hour of labour and subcontractor charge against that code as it happens. Compare actual with budget weekly. When the job closes, job profit is the price invoiced minus all its direct costs.
The quotation said the job would make RM15,000. At year end, the accounts say the business barely broke even, and nobody can say which jobs made money and which didn't. Materials were bought on one account for several sites, overtime went into the general payroll, and a subcontractor's extra charge arrived three weeks after handover. Without costs recorded against each job, every job looks fine until the profit is gone.
What is project cost tracking?
Project cost tracking, often called job costing, is recording every direct cost of a job against that job, and comparing the running total with the job's budget and price. Its purpose is to tell you, during the job and at the end, whether that specific job is making money.
In Bahasa Malaysia you might call it pengiraan kos kerja or simply kos projek. It doesn't replace your accounts. Your company books show whether the business made a profit; job costing shows which jobs produced it.
Which costs belong to a project?
Direct costs belong to a project: the costs you would not have incurred without that job. Overheads, such as rent, office salaries and software, are shared across all jobs and are covered by the margin you build into each price.
| Cost type | Examples | Where the figure comes from |
|---|---|---|
| Materials | Tiles, cabinets, cable, printing stock | Supplier bills and purchase orders |
| Subcontractors | Electrician, plumber, installer | Subcontractor invoices and progress claims |
| Own labour | Hours your staff spend on the job, including overtime | Timesheets or job sheets |
| Equipment and transport | Hire of scaffolding, lorry, tolls, parking | Bills and claims |
| Job-specific fees | Permits, building management deposits, delivery | Receipts |
| Overheads (not a job cost) | Rent, admin salaries, accounting fees | Covered by your margin |
Be strict about the boundary. If a cost would have happened anyway, leave it out of the job and cover it in your pricing. A break-even analysis shows how much margin you need across all jobs to cover overheads.
How do I work out the labour cost of a job?
Multiply the hours each person spends on the job by a loaded hourly rate: their wage per hour plus the employer's statutory contributions and any allowances. Overtime hours are costed at the overtime rate.
The Employment Act 1955 sets the method for the base rate. For a monthly-paid employee, the ordinary rate of pay for one day is the monthly wage divided by 26, and the hourly rate of pay is that daily rate divided by the normal hours of work. For overtime beyond normal hours, the Act requires at least one and a half times the hourly rate. Under the First Schedule as amended in 2022, that overtime provision doesn't apply to employees whose wages exceed RM4,000 a month, although their contract may still provide for it.
Example (illustrative): A site worker earns RM2,600 a month and works eight normal hours a day.
- Ordinary rate of pay: RM2,600 ÷ 26 = RM100 a day
- Hourly rate: RM100 ÷ 8 = RM12.50 an hour
- Overtime rate: RM12.50 × 1.5 = RM18.75 an hour
Then add the employer's EPF, SOCSO and EIS contributions on those wages, using the current rates from KWSP and PERKESO, to get a loaded rate. Keep it simple: one loaded rate per role is accurate enough for most SMEs.
How do I set up job costing step by step?
Give each job its own reference, budget it before work starts, and make recording costs against the reference a daily habit rather than a month-end task.
- Create a job code when the quotation is accepted, such as "J2609-014 Taman Molek kitchen". Use it on every purchase order, supplier bill, timesheet and claim.
- Budget by cost type using the same lines as the table above. The project planning guide shows how to build the budget with a contingency.
- Raise purchase orders against the job so committed costs are visible before the bill arrives.
- Record labour daily. A simple job sheet with date, name, job code and hours is enough. Separate normal and overtime hours.
- Code every bill on the day it arrives. Shared purchases, such as a bulk cement order, should be split across the jobs that use them.
- Review budget against actual weekly for every open job, including committed purchase orders not yet billed.
- Close the job properly: wait for the last subcontractor and supplier bills, then calculate the final profit.
Accurate records also help with compliance. The Companies Act 2016 (section 245) requires a company to make entries in its accounting records within sixty days of a transaction and keep them for seven years. Job-coded bills and timesheets meet that standard more easily than a shoebox of receipts. See record keeping in Malaysia.
How do I calculate whether a job made money?
Job profit is the amount invoiced for the job minus all its direct costs. Divide it by the amount invoiced to get the job's gross margin, then compare that with the margin you planned when quoting.
Example (illustrative): A Johor Bahru renovation contractor quotes RM48,000 for a kitchen and bathroom job, and the customer approves one change worth RM3,500 during the job. All amounts exclude SST.
| Cost line | Budget (RM) | Actual (RM) | Variance (RM) |
|---|---|---|---|
| Materials | 17,000 | 19,200 | (2,200) |
| Plumbing subcontractor | 6,500 | 6,500 | 0 |
| Electrical subcontractor | 4,000 | 4,600 | (600) |
| Own labour, normal hours (240 h planned, 260 h actual, at RM16 loaded) | 3,840 | 4,160 | (320) |
| Own labour, overtime (0 h planned, 60 h actual, at RM24 loaded) | 0 | 1,440 | (1,440) |
| Transport, skip bins, hire | 1,500 | 1,700 | (200) |
| Total direct costs | 32,840 | 37,600 | (4,760) |
| Amount invoiced | 48,000 | 51,500 | 3,500 |
| Job gross profit | 15,160 | 13,900 | (1,260) |
| Job gross margin | 31.6% | 27.0% |
The customer's change added RM3,500 of income, so on paper the job grew. But costs rose RM4,760, partly from the change and partly from extra tile wastage and 60 hours of overtime caused by a late delivery. The result is RM1,260 less profit than planned. The lesson isn't to refuse changes; it's to price each change with its own costs and to order long-lead materials early. For the difference between margin and markup when you price that change, see markup vs margin.
How often should I review project costs?
Weekly for every open job, and once more at closing. A weekly check gives you time to act: order differently, renegotiate a change, or warn the customer, while the job is still running.
At each review, look at three figures per job:
- Cost to date plus committed costs (purchase orders and subcontract amounts not yet billed).
- Estimated cost to finish, based on what's left, not on the remaining budget.
- Forecast profit, which is the price minus the two figures above.
If forecast profit drops below your minimum margin, decide what to do in that meeting. A supplier price rise found in week two can be passed on through a change request. Found after handover, it can only be absorbed.
How do progress claims affect job costing?
Progress claims change when cash arrives, not what the job earns. Track costs against the full job and keep a separate view of how much you have claimed, been paid, and spent, so that a profitable job doesn't leave you short of cash halfway through.
For construction work, the Construction Industry Payment and Adjudication Act 2012 (CIPAA, Act 746), in operation since 15 April 2014, gives an adjudication route for unpaid payment claims under written construction contracts. The party receiving a payment claim has ten working days to respond. Our guide to accounts receivable collections covers payment claims and chasing in more detail.
Keeping each job's paperwork together makes these reviews faster. In HumbleBear, a job's quotation, purchase orders and invoice can be linked to its card in a Space, so the documents you need for the cost review are in one place.
Frequently asked questions
What is the difference between job costing and accounting?
Accounting records the whole business's income, costs, assets and liabilities, and produces its financial statements. Job costing assigns direct costs to individual jobs, so you can see which jobs made money. Both should use the same supplier bills and invoices, so the figures agree.
Should overheads be included in job costs?
Usually not for a small business. Keep job costs to direct costs, and cover overheads like rent and admin salaries through the margin you build into every price. Including a share of overheads in each job can make good jobs look worse and hides what each one really earns.
How do I cost my own time as the business owner?
If you work on the job yourself, include your hours at a fair hourly rate, even if you don't pay yourself a salary by the hour. Otherwise jobs that depend on your labour look more profitable than they really are, and you may underprice similar work.
What is a good gross margin for a project?
It depends on your industry, overheads and how risky the work is. Work out the margin you need across all jobs to cover overheads and leave a profit, then set it as your minimum when quoting. See profit margin explained for how to calculate it.
When should I calculate the final profit on a job?
After the last supplier bill, subcontractor invoice and timesheet for the job have been recorded, not on the day of handover. Late bills are common, so wait a few weeks or mark the profit as provisional until everything is in.
Sources
- Employment Act 1955 (Act 265), updated text as at 1 January 2023, sections 60A(3) and 60I, Department of Labour Peninsular Malaysia (JTKSM)
- Employment (Amendment of First Schedule) Order 2022, P.U. (A) 262/2022, JTKSM
- SSM: Companies Act 2016 (Act 777), section 245
- Adjudication under CIPAA 2012, Asian International Arbitration Centre
- KWSP (EPF): Employer mandatory contribution
- PERKESO (SOCSO): Contributions